Subscribe to our Mailing List



The Southend Lane Action Movement

Welcome to the SLAM! Website

Who We Are.

We're an action group from Newent in Gloucestershire, set up to coordinate the local residents' response to the unauthorised occupation and development of just under 6 acres of agricultural land on Southend Lane.

Our Aims.

  • Oppose Enforcement Appeal APP/P1615/C/09/2107067 lodged against the Forest of Dean District Council's order which gave 28 days notice that the site must be returned to its original condition and be vacated within 12 weeks.
  • Assist the FODDC and Gloucestershire County Council in their efforts to make proper provision within the Forest of Dean for Gypsies, Travellers and their families, so they don't feel they have to resort to breaking the law in order to set up home.

Public Inquiry Results

Appeal Decision ; Land at Southend Lane, Newent

ref APP/P1615/C/09/2107067

Back at the begining of December 2009, legal teams representing SLAM, The Forest of Dean District Council and Mr R. Jones met at a Public Enquiry held by the Planning Inspectorate. All three days were well attended and although the proceedings were, at times, quite difficult to follow, the general consensus of SLAM members was that each party had been given ample opprotunity to put their case to the inspector.

We were assured that a judgement would be made fairly quickly and indeed by the begining of January 2010, we learned that the Planning Inspectorate had granted temporary planning permission until January 2012. This was felt to be the shortest practical timescale for vacating the site and returning it to the same condition it was in prior to 22nd May 2009.

In short - we won!

Thanks to a robust response from the District Council and our own legal team's insightful analysis, common sense seems to have prevailed at Southend Lane. The judgement document is pretty complex and can be found in full at the FoDDC's website but we've prepared a simplified version which you can read below:

Main Issues and Responses to Them

  1. Suitability of the highway access to the site and whether improvements should be required as sought by the highway authority.
    Objection on highway grounds is not justified as improvements can be carried out; Passing Places pp1 and pp3, and the addition of a street light are deemed effective in removing highway safety concerns.
  2. Effect of the development, including highways works, on the landscape and character of the area.
    There would be visual harm and landscape impact because of the size and openness of the development, and the intention to build day rooms etc.
  3. Effect on the setting of the three listed buildings.
    The setting of the buildings includes the appeal site, and its use as a caravan site is detrimental to the character of the setting of the buildings.
  4. Whether biodiversity effects, particularly the probable effect on great crested newts can be met by condition.
    No available evidence that the probable effect of the development would be grounds to dismiss the appeal.
  5. Can drainage requirements be met adequately by imposing conditions.
    Uncertainty about drainage arrangements, including lack of information from appellents in support of the proposals, are not considered to be grounds to dismiss the appeal.
  6. The need for additional gypsy pitches nationally and locally.
    26 pitches are required, and weight must be given to the Councils persistent and substantial slippage in its programme regarding development plan documents regarding such sites. There is no evidence that the Councils’ latest timetable is to be relied upon, but the employment of a dedicated officer seeking approval of sites is to be noted.
  7. Whether alternative sites are available for the occupiers.
    If the appeal is dismissed, the occupiers will have to leave the site. There are not suitable, available alternatives for long term accommodation currently to be relied upon.
  8. Advantages/disadvantages of the development in relation to sustainability, para 64 of Circular 01/2006.
    Allowing the appeal would avoid damage caused by unauthorised encampment, and the site offers good access to necessary services.
  9. Weight given to personal circumstances of the occupiers.
    There is nothing unusual about the occupiers, therefore particular circumstance does not alter the weight given to providing or removing a settled base.

Conclusions

Permanent vs temporary Planning Permission.

  • The permanent harm if planning permission were granted, is strongly against the grant of said permission because the location and character of the site and its surroundings are not suitable for a development of this size.
  • Temporary planning permission avoids adverse effects on the occupiers, of the absence of suitable alternatives, and is the least worst result. It will need to be for the shortest time possible and will require considerable effort by the LPA to bring forward other sites. There is doubt that the suggestion that the occupiers all wish to seek a site together is so compelling as to preclude alternatives.
  • Two years is appropriate, as it would be reasonable to expect circumstances to have changed by then, and the harm done would not be lessened but would be of shortened duration. The site will remain pretty much as seen on 4th Dec 2009.
  • Works of mitigation in relation to highway, landscaping and biodiversity will not be achieved.

Planning permission is therefore granted on the land developed, until 31st January 2012, but the enforcement notice is not quashed.

Conditions

  1. Use is for a limited time ending 31st jan 2012. After this date the land shall be restored to its former condition, prior to the development taking place.
  2. Only gypsies/travellers occupy the site.
  3. No more than 13 pitches, with no more than 2 caravans, one of which may be a mobile home.
  4. No vehicles over 3.5 tonnes to be stationed, parked or stored on the site.
  5. No more than one commercial vehicle per plot, not to exceed 3.5 tonnes.
  6. No commercial activities to take place on site.
  7. Except for conditions under no 8. the operational development permitted is only that present on 4th Dec ’09.
  8. Use shall cease and all materials etc to be removed within 28 days of failure to meet any of the requirements set out below.
    • Within 2 months of the date of decision, schemes for siting of caravans, ancilliary structures, means of foul and surface water drainage, proposed and existing external lighting and nature of fences to be erected shall have been submitted to LPA including timetable for implementation.
    • If within 11 months LPA has not approved site development scheme, or it has been refused by the LPA, or a reason for delayed decision fails to be made within the timescale, an appeal shall have been made to and validated by the Secretary of State so that the site development scheme may be approved by the Secretary of State.
  9. There shall be no external lighting, or fences, gates or walls exceeding 1m in height other than approved in no 8.

The enforcement notice is to be varied to require the land to be returned to its former condition, and planning permission is refused on the remaining land.

A Simple Guide to the Enforcement Appeal

The Background

On Friday the 22nd May 2009 (a Bank Holiday weekend) at around 5.15pm, local residents were horrified to see large numbers of vehicles and men plough through a hedgerow bordering a piece of agricultural land on Southend Lane, and begin to transform it into a vast building site.

The field had been recently sold, and for some months neighbours from nearby houses had been in contact with the Forest of Dean District Council hoping to prevent just such a breach of planning law occurring. Unfortunately until events like those now unfolding in the field were under way, there was nothing which could be done.

Because the field’s new owners had chosen a Bank Holiday weekend to commence their unauthorised development, a majority of the work was complete before any action could be taken, a judge having refusing to grant an Interim Order requested by the Council on 23rd May. By the next week a sizeable chunk of the field had become a caravan park with a tarmacked access road and 13 large plots with hard standings, mains electricity hookups, mains water and access to portaloos or one of their newly installed septic tanks.

What Action Has Been Taken?

In the absence of prior planning permission, the FODDC issued an Enforcement Notice giving 28 days notice that the site must be returned to its original condition and be vacated within 12 weeks. Perhaps unsurprisingly, the people on site ignored the order and have lodged an Appeal which will be decided at a public enquiry later on this year. At present this Appeal against the Enforcement Notice is our pressing concern, because if upheld the site is likely to become a permanent fixture.

It should also be noted that currently only about half the field has been developed so there’s huge scope for expansion.

On What Grounds did the Council Issue the Enforcement Order?

The full details of the notice, plus a detailed explanation of the more complex points relating to planning policy and guidelines can be found in the Details section, but two of the main points which you may feel affect you as a local resident are as follows:

1 This unauthorised development is harmful to the visual amenities of the area.

Anybody viewing the site in the course of their daily life can see that it’s not at all in keeping with its surroundings and could be considered detrimental to an irreplaceable natural resource - the countryside. It doesn’t matter whether you can see it from your house or indeed from any one of numerous viewpoints whilst out walking the dog or just taking a stroll along one of the nearby public footpaths, your opinion matters!

2 This unauthorised development is prejudicial to interests of road safety.

With upwards of 20 caravans currently on site and scope for this to greatly expand in the future, there’s been a huge increase in road and foot traffic along a narrow lane - a no through road. There’s also the wider issue of the added volume of traffic on Culver Street and on into the town itself, along roads with poor pavement provision and many narrow sections without passing places.

What next?

Although totally supportive of the Gypsy and Traveller families’ right to properly provisioned sites, SLAM! wholeheartedly agrees with the FODDC’s assertion that this development is unsuitable in this location.

A public enquiry will be held later this year and anyone with an opinion was given the opportunity to express themselves. Large numbers of you did so and SLAM! would like to thank you for taking the time to make your make your feelings known to the Planning Inspectorate.

The deadline of 11th August has now passed.

Further Information

Click on the link below to download a booklet provided by the Planning Inspectorate website. It contains useful info about the Inquiry process itself as well as some insights into the actual proceedings:

Guide to taking part in planning appeals proceeding by an inquiry

We also have more detailed information about some of the more technical aspects of the Visual Amenity part of the FODDCs Enforcement Notice on this seperate page:

Details of the Enforcement Appeal

Residents’ Meeting

Notes from Residents’ Meeting at Newent Community Centre

Monday 8 June 2009 6.30 pm to 8pm
Travellers/Gypsies unauthorised encampment at Southend lane, Newent

Present

  • Councillor Len Lawton - Local District councillor (Chairman of the meeting)
  • Councillor Peter Amos - District councillor and Cabinet member (Planning and Housing)
  • Sue Pangbourne - Interim Head of Paid Service
  • Peter Hibberd - Strategic Director
  • Peter Williams - Group Manager (Planning and Housing)
  • Marie Rosenthal - Group Manager (Legal and Democratic Services)
  • Dawn Evans - Assistant Solicitor
  • Tony Wisdom - District Council Press Officer
  • Paul Kenyon - Gloucestershire County council Traveller Liaison Officer
  • Press Representative
  • Two Community Police Officers
  • Approximately 125 invited local residents

1.Introduction

1.1 Sue Pangbourne opened the meeting by explaining that she understood the concerns over gypsy sites in the district and in particular in the area, she confirmed she would explain what is happening on the site so far, what the Council’s action is and has been, and what the Council’s action hopes to achieve.

1.2 Sue went on to explain the relevant planning legislation namely the Stop Notice and Enforcement Notice, when they both took affect, what they precluded, and what the maximum fine in the Courts was for breaching the Notices if found guilty. Sue explained the wider issues, that as well as being a breach of planning control, the council also needed to address the permanent pitches that were required by the GTAA in this district since July 2008 and the details laid down in the emerging regional spatial strategy for the South West. She also explained that the planning process was lengthy.

2.The Planning Context

2.1 Peter Williams gave a basic introduction to the issues on site and then went on to read out answers to the questions that had been presented to the planning section over the last few weeks.

Read more...

Southend Lane Press Coverage

This is Gloucestershire (and in print in the Citizen) - 6th August 2009

Travellers move on to Gloucester playing fields

This is Gloucestershire - 4th July 2009

Battlelines drawn with gypsies in Newent

This is Gloucestershire - 25th June 2009

I wouldn't mind gipsies near me

This is Gloucestershire - 23rd June 2009

Travellers 'Forced to Invade Sites'

This is Gloucestershire - 16th June 2009

Move travellers to Cinderford site

Ledbury Reporter - 11th June 2009

Residents form action group over travellers' site

Daily Mail - 11th June 2009

Traveller sites are booming as they exploit the Human Rights Act

Read more...

More Articles...

Page 1 of 2

Start
Prev
1